Karnataka Wind Installer and DISCOM Spar Over Wheeling of Energy to Open Access Consumers
The Commission ordered BESCOM and GESCOM to redo the energy bills from June 2018 to March 2019
June 4, 2020
/ Wind
Follow Mercom India on WhatsApp for exclusive updates on clean energy news and insights
Save
The Karnataka Electricity Regulatory Commission (KERC) has ordered that Golden Hatcheries, a company that had installed a 3.2 MW wind power project, should be granted its due credits for the energy injected into the grid from June 12, 2018, to July 6, 2018.